Iona Island WWTP

CLIENT

Metro Vancouver

LOCATION

British Columbia

DELIVERY MODEL

Design-Bid-Build

PRIME CONSULTANT

Jacobs

SECTOR

Environmental, Water & Wastewater

PROJECT VALUE

$23.8 million

COMPLETION DATE

June 2017

Project Overview

This upgrade project constructed a primary sludge screening and degritting facility, a primary sludge thickener and pump building, an odour control system, and other related work. Due to its proximity to the Fraser River, the project team implemented several environmental protection measures throughout the construction period.

The project also involved soil densification, dewatering, excavation, site services, building mechanical installations, electrical distribution, instrumentation, and control systems. Interconnecting piping between the new and existing facilities’ mechanical, electrical, and other support systems was required. Coordination with other contractors and plant operators was a critical element of the project.

An aggressive schedule was set for the removal of 27,000 m³ of preload sand and the installation of approximately 4,900 timber piles to achieve the design soil densification before construction began. We used a deep well dewatering system to facilitate the construction of utilities and deep foundations.